Lamu Coal Plant NEMA License

Copy of the license issued by the National Environmental Management Authority (NEMA) to approve the Lamu Coal Power plant on September 9, 2016. Download PDF Version.

ESIA of The Lamu Coal Power Plant

The official Environmental and Social Impact Assessment Study (Known as the EIA or ESIA) of the 1.050 Lamu Coal Power Plant undertaken by Amu Power and submitted to the National Environmental Management Authority.   DOWNLOAD REPORT BELOW 00 Project Details 01 Executive Summary 02 Policy Legal and Institutional Framework 03

Delays hit 982MW Lamu coal plant on Nema approval hitch

Source: Business Daily Africa The construction of Kenya’s first coal-fired power plant faces delays due to the failure to get approval from the environment watchdog and delays in compensating those to be displaced by the electricity project. Construction of the 981.5-megawatt plant in Lamu was set to start September 30